How to scale an electric truck fleet within your depot’s power capacity
A successful electric truck fleet trial does not automatically mean the depot can support the next ten vehicles. More trucks need more charging energy, but the greater challenge may be delivering it between their return and departure times, without creating a new demand charge or doing so during peak tariff times.
For South African fleets, expansion can also depend on municipal or Eskom connection capacity, site electrical upgrades and approval processes. Before ordering more vehicles, establish what the depot can support today and which changes must be completed before the next phase arrives.
Measure the power available during your charging windows
A depot’s supply rating does not tell you how much power is available for fleet charging.
Refrigeration, conveyors, forklifts and other equipment in your building share the connection. Their demand changes throughout the day. Spare capacity at midnight may be very different from spare capacity when trucks return in the afternoon.
Review the site’s measured load profile alongside its contracted supply capacity and the limits of its electrical infrastructure. Monthly electricity consumption alone cannot show when charging will compete with other loads.
Be careful with units. Connection limits may be specified in kilovolt-amperes (kVA), while chargers are commonly rated in kilowatts (kW). These are not interchangeable; the assessment must account for power factor and the relevant equipment limits.
Establish the power available to charging across the operating day, allowing a margin for changes in site demand.
Calculate charging demand for your expanded electric truck fleet
Use operating data from the existing electric vehicles, then add the proposed vehicles and routes. Longer distances, heavier payloads or shorter turnaround times may produce a different charging requirement from the original trial.
For each vehicle, establish:
How much energy it needs before its next departure, including the agreed operating reserve.
When it can actually be plugged in, allowing for unloading and other depot activities.
The charging power its battery can accept, including reductions during the session.
Which other vehicles will need charging during the same period.
This turns a vehicle order into a charging schedule that can be checked against the site’s available power.
Example: why enough daily energy does not guarantee enough charging time
Consider a hypothetical depot with 200 kW available at the charging-system input throughout an eight-hour overnight window, after other site loads and an operating margin have been allowed for.
Assume each truck requires 100 kWh at that same charging-system input to replenish the energy used on its route. Charging losses are therefore already included in this example.
Fleet size | Energy required overnight | Average charging input over eight hours |
|---|---|---|
5 trucks | 500 kWh | 62.5 kW |
10 trucks | 1,000 kWh | 125 kW |
15 trucks | 1,500 kWh | 187.5 kW |
At first glance, all three fleet sizes fit below 200 kW. But the 15-truck phase uses almost all the available overnight energy capacity: 1,500 kWh out of a theoretical 1,600 kWh.
Now suppose six of those trucks return late and each needs its 100 kWh within the final two hours before departure. Together, they require 300 kW on average during that period. The site can supply only 200 kW to charging.

These are illustrative calculations, not a depot design or a vehicle performance claim. They assume adequate connectors and charging equipment. Actual planning must also account for vehicle charging curves, equipment availability and changes in site demand.
Before adding the trucks, the operator must resolve the two-hour shortfall through a workable change in operations or additional power. Buying more chargers alone will not increase the power available to them.
South African power-supply hurdles that can delay fleet expansion
Start by confirming who supplies the depot: Eskom directly, the municipality or a landlord through a shared connection. Requirements differ by distributor and site. The following checks identify dependencies that can affect the vehicle rollout:
The contracted supply may be lower than the new fleet requires. For Eskom customers, increasing Notified Maximum Demand (NMD) requires an application, evaluation and a revised supply agreement. Check the equivalent requirements with a municipal supplier. Installed charger capacity is not permission to draw more power, and exceeding the agreed demand can have tariff consequences. Eskom NMD guidance
The local network may need reinforcement. Ask the distributor whether the feeder, transformer and connection can support the requested increase. A larger supply may involve network work and connection charges, including upstream costs. Obtain a site-specific assessment before treating additional grid capacity as available. Eskom business connections
The depot’s own electrical installation may be the constraint. Have the electrical designer check the transformer, main distribution board, cable capacity, voltage drop and protection arrangements for the expanded load. A larger utility allocation does not increase the ratings of equipment already on site. Plan installation shutdowns around dispatch and other critical operations.
Connection work can depend on space, permissions and construction. Cable routes, wayleaves and space for transformer or switchgear facilities may need to be resolved. Leased depots must also establish the landlord’s approval and responsibility for the work. Eskom’s process includes design, routing and approvals; regional guidance also identifies customer-built substation facilities where applicable. Confirm these dependencies and the delivery programme before fixing vehicle deployment dates. Eskom connection process, Cape Town connection guidance
Solar and batteries bring connection requirements of their own. They are not a shortcut around electrical approval. For example, Cape Town requires authorisation for solar PV and battery installations in its supply area, with approved inverters and professional sign-off under its published requirements. Confirm the applicable process, export limits and protection requirements with the actual distributor. Cape Town energy guidance
An outage can remove the charging time the plan relies on. Test how the fleet would recover from a local fault or planned interruption. Check whether backup equipment can support charging alongside essential site loads, and how charging restarts when supply returns. Existing warehouse backup capacity should not be assumed sufficient for an expanded electric fleet.
Record each required approval or upgrade, who is responsible and when it must be ready. This makes the electrical work part of the fleet rollout programme rather than a problem discovered after delivery.
Use managed charging before assuming more grid power is necessary
Managed charging allocates available power according to vehicle energy needs and departure times, while responding to changes in other depot loads. A truck leaving in two hours may need priority over one parked until morning.
Software such as Aeversa's preferred charging software, Ampcontrol, can coordinate charging with building consumption, solar generation and battery storage. This can make better use of the existing connection, provided the vehicles still have enough time to receive their required energy. Ampcontrol platform
In the worked example, scheduling alone cannot supply 600 kWh through a 200 kW limit in two hours. The fleet needs a longer charging window, an earlier charging opportunity or additional power during that period.
Match additional infrastructure to the constraint
When the next fleet phase exceeds the depot’s capability, identify precisely what is missing before selecting equipment.
Constraint identified | What to assess |
|---|---|
Vehicles wait for an available connector, but the site has spare power | Additional charging points and a workable bay layout |
Several vehicles need high power for a short period | Charging priorities, operational changes or battery support |
Daytime charging overlaps with suitable solar generation | Solar PV integrated with charging controls |
Charging needs more energy than the site can supply across the available window | Additional energy supply, longer charging windows or a connection upgrade |
Battery storage can support short periods of high demand, but it must be sized for both discharge power and usable energy. It also needs a credible opportunity to recharge before the next charging peak.
Solar PV can reduce grid purchases and contribute power while generating. Its annual output does not establish how much power will be available for a particular departure deadline. Test low-solar conditions as well as expected production.
What TFS’s phased fleet expansion shows
Aeversa’s September 2026 announcement describes Takealot Fulfilment Solutions (TFS) growing from a single-vehicle trial to 10 grid-charged trucks, then 21 vehicles following the integration of solar PV and battery storage, and subsequently 28 vehicles across three cities.
At the reported 28-vehicle stage, solar supplied 50% to 80% of daily fleet charging energy, with storage moving excess daytime generation into evening charging. Engineering News: TFS fleet expansion
The expansion paired additional vehicles with changes to the energy system. It is a useful example of staged growth, not a capacity or renewable-energy forecast for another depot.

Agree the conditions for the next fleet phase
Before committing to vehicle delivery, confirm that:
The charging plan meets dispatch requirements, including late returns, high-energy routes and a charger being unavailable.
The required supply and site work will be ready, with responsibility assigned for approvals, construction and commissioning.
The business case includes the full enabling cost, including electrical upgrades, software, maintenance and changes to demand or capacity charges. Compare options against the same operating schedule; our charging cost per kilometre guide explains which costs to include.
After expansion, track departure readiness, charging queues, grid demand and how often power restrictions delay charging. Use those results to plan the next vehicle phase.
Assess depot power before committing to fleet growth
Aeversa’s Power Demand Assessment maps the site’s energy demand and supply to help establish spare capacity and constraints.
Combined with the proposed fleet’s routes and charging windows, that information provides a basis for deciding how many additional vehicles can be supported and which changes need to come first. Confirm the scope of fleet modelling and infrastructure design alongside the site assessment.
Bring your electricity bills, available load data, current charging records and proposed vehicle rollout to the initial discussion.
Written By:
![]() | John Henry Ford Sales Manager AEVERSA |
Author Bio:
John is the Sales Manager at Aeversa, where he specialises in fleet electrification and sustainable energy solutions. With a strong background in the EVSE and automotive industries, John has led initiatives that integrate electric vehicle charging infrastructure with renewable energy sources, such as solar power and battery storage.
His work focuses on enhancing operational efficiency and reducing costs for logistics and distribution fleets. John is passionate about advancing clean transportation technologies and has been instrumental in projects that demonstrate the practical benefits of fleet electrification in South Africa.








Comments